Inside View vs Outside View

Every project estimate, every revenue forecast, every commitment.

AxisInside viewOutside view
Source of estimateDetails of this specific caseDistribution of similar past cases
FeelDetailed, rigorous, optimisticGeneric, blunt, pessimistic
Usually right when…You know the execution details wellThere's a defensible reference class
Example

Inside view: «we'll launch in 8 weeks». Outside view (looking at 6 similar past projects): median was 16 weeks, max 32. The truth lives somewhere in between - and the outside view almost always wins.